Green signal for NHAI project
HC permits the NHAI to complete the project of Tiruchy-Karaikudi NH 2010 bridge work.
Chennai: The Madras high court has permitted the National Highways Authority of India (NHAI) to complete the remaining project of the Tiruchy-Karaikudi NH 2010 bridge work subject to the condition that it should not contravene the undertaking given to the court in respect of preservation of water bodies.
Justice T. Raja allowed a batch of petitions from the NHAI while quashing the three orders of the state PWD passed in September, October and November 2012, refusing ‘no-objection certificate’ to NHAI for the balance of the bridge project.
The judge said in respect of the completed project and the undergoing project, if any deepening of desilting or any other restoration work was required, NHAI should carry it out by incurring the entire expenditure required.
Concurring with the submissions of additional solicitor general P. Wilson, the judge said there was no justification to stall the remaining minor work and, hence, the impugned proceedings have to be quashed.